AHM DEALER IMAGE PROGRAM DESIGN PROCESS AND TIMELINES
GENERAL
Changeup Inc (CU) will present your Design Intent Documents (DID) to review the process and submittal requirements.
A. Invitees: Architect of Record (AOR), PM team, General Contractor (GC), and other relevant personnel
Two-Step Compliance Process:
A. Preliminary drawing (PD) submittal and approval to CU and city planning (AHJ)
B. Construction drawing (CD) submittal and approval to CU and city building department (AHJ)
PRELIMINARY DRAWING (PD) SUBMITTAL
AOR shall prepare and submit PD set to CU within 8 weeks of DID presentation (preliminary acceptance required by CU Prior to AHJ submittal)
Files (PDF and CAD) required, at minimum, as a part of PD submittal based on DID package:
A. Site plan
B. Floor plan
C. Exterior elevations
Once accepted by CU, PD set submitted for AHJ review
A. Any drawing revisions required by AHJ must be re-submitted to CU for review and approval
Once PD set is approved by AHJ, AOR proceeds with CD set
CONSTRUCTION DRAWING (CD) SUBMITTAL AND APPROVAL
Submit complete CD set (PDF) to CU to verify compliance
A. Compliance review letters are provided with comments for correction
B. Comments must be addressed and revised drawings or written justification for exceptions submitted to CU
C. Letter of compliance (LOC) will be published once all corrections or exceptions are addressed and considered
Compliant CD set to become expectation for completed facility
A. Deviations from compliant set shall be submitted to CU for consideration
B. Deviations not approved by CU could jeopardize compliance status
CD set shall include the following, minimum:
Title sheet
General notes and code data
Architectural site plan
Floor plan
Floor finish plan
Interior finish schedule
Furniture, fixture, and equipment plan
Furniture and fixture schedules
Interior elevations
Door schedule
Window schedule and type
Reflected ceiling plan
Lighting plan
Light fixture schedule
Exterior building elevations
Exterior finish schedule
Building sections
Enlarged floor plans (as needed)
Floor power plan
Plumbing fixture schedule
Additional sheets as required
4. Approved CD set submitted to AHJ for plan review
5. Once approved, AHJ will issue a permit and construction can begin on dealership project
6. Upon construction completion:
A. Dealer shall request facility inspection through OEM Regional manager
B. CU conducts final inspection based on the approved compliance CD set submitted and previously approved exceptions